Month -> Events/ Activities
November/ December 2008 ->
Research on solar cells/ photovoltaic
February 2009 ->
making and testing of solar car
18th March 2009 ->
training conducted by TP lecturers
23rd March 2009 ->
calculations for photovoltaic modules
24th to 27th March 2009 ->
measuring the intensity of the sunlight
2nd April 2009 ->
Prototype Development #1: Site Survey
10th April 2009 ->
Prototype Development #2: Research and Ideation
30th April 2009 ->
Prototype Development #3: Scale Model
5th May 2009 ->
Light Intensity Testing: Raw Data & Plotting of Results
11th May 2009 ->
Prototype Development #4: Arrival of the actual prototype
24th June 2009 ->
Delivery & Testing of Solar Water Fountain System
7th July 2009 ->
Training on Operations & Maintenance of Solar Water fountain
30th Oct 2009 ->
Sharing Session with 2E2 Students (post-exam)
29th Jan 2010 ->
Training Session with Sec 2 Students
9th to 20th Feb 2010 ->
Peer Teaching Session for Sec 2 Students
Siti: There were a lot of complications while doing the measurements at the water fountain . We had to
ReplyDeletego to and fro from the D&T workshop and the water fountain area because we had calculated the length
wrongly . It was tiring . To make the model looked real , we also went out with Mr Kumar to Vista Point
to buy the materials needed for the model . Since the project was conducted in the middle of our exam
period , there was a lot of postponing and we had to delay the making of the model
Jie Lun commented :
ReplyDeleteThe school fountain is quite cramp beacuse it is hard to measure the correct reading for the fountain as there is too many plants around it. But we managed to resolve the problem.
So , we have come up with a mini fountain which uses solar power that allow no electricity used. After we have decided the scale of the mini model , we went out to buy materials we needed. We bought a mat to be the grass of the mini model , a styrofoam for the base and a green plastic cardboard. We spend around 30minutes to buy all the materials and head back to school. The mini model was delayed and it was only done immediately after our last exam paper. It was a rush , but we still manage to complete it. :D